• Home
  • Projects
    • About Us
    • Safety
    • Suppliers
    • Subcontractors
    • Letters of Recommendation
  • Contact Us
Menu

CQ Contractors

  • Home
  • Projects
  • About
    • About Us
    • Safety
    • Suppliers
    • Subcontractors
    • Letters of Recommendation
  • Contact Us

SHORING + EXCAVATION

LAH - Pine Lane Sewer Diversion

Project Name:Guadalupe Creek Fish Ladder

Location:Campbell, CA

Owner: Santa Clara Valley Water District

Owner Contact: Tim Bramer – (408) 265-2607

Prime Contractor:  Con-Quest Contractors, Inc.

Prime Contractor Contact

Architect/Engineer: Owner

Architect/Engineer Contact: N/A

Construction Manger Contact: N/A

Description Of Project Scope: All work performed within Guadalupe Creek. Design and implement a gravity water diversion around work capable of handling 100 cfs of water flow in creek, including a back up pump system. Installation of a cast in place concrete fish ladder structure, erosion control, slope protection, rip-rap plunge pool, 5 new weir structures and modify existing. HAZ-MAT excavation and controlled disposal of 460 tons of Mercury contaminated soils. Monitor and maintain sensitive wildlife area within works limits discovered during construction.

Original Bid Amount: $819,620.00

Change Orders: $ 18,624

Claims $ 0

Final Contract Value: $838,244

Original Start Date: October 29, 2009

Original Duration: 80 Calendar Days

Original Completion Date: August 11, 2008

Time Extension Granted In Days: 0

Actual Completion Date: October 29, 2009

Liquidated Damages: None

Recordable Accidents: Zero

Lost Time Accidents/ LAF: Zero / 0

OSHA Violations/ Fines: None

DOWNLOAD PDF

pine-lane-sewer.jpg

Sunnydale Auxiliary Sewer

Project Name: Sunnydale Auxiliary Sewer Project

Location: San Francisco, CA

Owner: San Francisco Public Utilities Commission

Owner Contact: Glen Cross -

Prime Contractor: Super Excavators

Prime Contractor Contact: Doug Stoffel 414-491-1850

Architect/Engineer: Jacobs Engineering

Architect/Engineer Contact: N/A

Construction Manger Contact: N/A

Description Of Project Scope: Drive 32,000 SF of Sheet Pile; Excavate 6,000 CY to a depth of 32' & backfill same including bracing for a 12’ dia. Tunnel Launch Pit. Drive 6,300 SF of Sheet Pile; Excavate 1,250 CY to a depth of 28' & backfill same including bracing for 12’ dia. Tunnel Receiving Pit / 96” Micro Tunnel Launch Pit. Construct a 25 x 30 x 28'd Solider Pile & Lagging for 96” Micro Tunnel Receiving Pit. Construct four concrete junction/tie-in structures totaling 1,000 CY. Installed, Maintained and Removed Dewatering System for all 3 Pits with a total of 18 pumps to depths of 60’. Installed 108" S.S. Pipe for Tie Ins. (Be Specific Qty's & Sizes)

Original Bid Amount: $ 3,169,590.00

Change Orders: $ 724,000.00

Claims $ ---0---

Final Contract Value: $ 3,893,590.00

Original Start Date:  September , 2010

Original Duration: 560 Calendar Days

Original Date: March, 2012

Time Extension Granted In Days: N/A – C-QC was a subcontractor on this project.

Actual Completion Date: January, 2012 – for C-QC’s work

Liquidated Damages None

Recordable Accidents/ RAF: Zero / 0

Lost Time Accidents/ LAF: Zero / 0

OSHA Violations/ Fines: None

DOWNLOAD PDF

sunnydale.jpg

Agua Fria, Toroges and Agua Caliente Creek Improvement

Project Name: Agua Fria, Toroges and Agua Caliente Creek Improvements

C115 (11029)

Location: Fremont, CA

Owner: Santa Clara Valley Transportation Authority – VTA

Prime Contractor: Con-Quest Contractors, Inc.

Prime Contractor Contact: Paul Loukianoff – 415-206-0524

Architect/Engineer: HNTB Corporation

Architect/Engineer Contact: N/A

Construction Manger Contact: N/A

Description Of Project Scope:

Work under this project consisted of installing a precast UPRR railroad bridge, over 3,200 CY of CIP concrete including 1,100 Liner Feet of retaining wall, 1,20 Lf of CIP box Culvert, 250 LF of precast concrete box culvers and new inlet structures for a new 78” RCP and existing 81” RCP. The new 78” RCP was installed by micro tunneling under active UPRR track which required soil monitoring. Launch and receiving pit were 22’ deep using beam and sheet piles.  In addition C-QC installed 1,000 TF of UPRR track with 2 turnouts. 

Original Bid Amount: $7,673,890.00

Change Orders: $1,351,341.20

Claims: $  ---0----

Final Contract Value: $8,912,611.65

Original Start Date: June 2011

Original Duration: 471 – Calendar Days

Original Completion Date: September 2012

Time Extension Granted In Days: 304 – Calendar Days

Actual Completion Date: September 2013

Liquidated Damages :None

Recordable Accidents/ RAF: Zero / 0

Lost Time Accidents/ LAF: Zero / 0

OSHA Violations/ Fines: None

DOWNLOAD PDF

Project Brochure - Job 031 Agua Fria.jpg
prev / next
Back to Shoring + Excavation
1
LAH - Pine Lane Sewer Diversion
1
Sunnydale Auxiliary Sewer
1
Agua Fria, Toroges and Agua Caliente Creek Improvement
pipeline.jpg
structures.jpg
rail-trackwork.jpg
duct-bank.jpg
creeks-canals.jpg
concrete-flatwork.jpg