• Home
  • Projects
    • About Us
    • Safety
    • Suppliers
    • Subcontractors
    • Letters of Recommendation
  • Contact Us
Menu

CQ Contractors

  • Home
  • Projects
  • About
    • About Us
    • Safety
    • Suppliers
    • Subcontractors
    • Letters of Recommendation
  • Contact Us

CONCRETE + FLATWORK

5 Fulton Ductbank

Project Name: 5 Fulton Ductbank Construction Project MR-1242

Location: San Francisco, CA

Owner: San Francisco Municipal Transportation Agency

Owner Contact: Victor Yuen 415-706-1142

Prime Contractor: Con-Quest Contractors, Inc.

Prime Contractor Contact: N/A

Architect/Engineer: N/A

Architect/Engineer Contact: N/A

Construction Manger Contact: N/A

Description Of Project Scope: Installed 7,325 LF of 2 -2” & 6 – 6” HDPE concrete encased ductbank. Exc, Set and Backfilled 15- 6’ x 8’ x 8’ vaults for Traction Power System along Fulton Street between 32nd and 8th Avenues. Install 2,670 LF of GRS conduit to new and existing Feeder Trolley Poles. Install 12 new trolley poles & foundations. Modify existing overhead contact system.Install 1425 CY of new concrete street base; ground 103,680 SF of existing asphalt; and, place 1,605 tons of new asphalt. Install 1,700 SF of sidewalk; 400 LF of curb & gutter; and, 19 curb ramps.

Original Bid Amount: $ 6,053,975.00

Change Orders $ - 550,000.00

Claims $ ---0---

Final Contract Value: $ 5,453,975.00

Original Start Date: January, 2011

Original Duration: 485 Calendar Days

Original Completion Date: May, 2012

Time Extension Granted In Days: N/A

Actual Completion Date: January, 2012

Liquidated Damages None

Recordable Accidents/ RAF Zero / 0

Lost Time Accidents/ LAF Zero / 0

OSHA Violations/ Fines: None

DOWNLOAD PDF

Project Brochure - Job 025 No. 5 Fulton Ductbank.pub.jpg

Bernal Heights Street Improvements

Project Name: Bernal Heights

Location: San Francisco, CA

Owner: SFPW

Owner Contact: Joe Timinare

Prime Contractor: Con-Quest Contractors, Inc.

Prime Contractor: Contact 415.206.0524

Architect/Engineer: Owner

Architect/Engineer Contact: N/A

Construction Manger Contact: N/A

Description Of Project Scope: Reconstruct and Widen 230 LF of Roadway. Construct 140 LF of 8’ tall CIP Retaining Wall on 24”x 30’ deep CIDH pile. Construct 420LF of Wood Retaining wall ranging from 2 to 6’ Rail. Construct 240 LF of CIP stairs and walk way

Original Bid Amount: $583,325

Change Orders: $61,669

Claims: $ ---0---

Final Contract Value: $644,994.63

Original Start Date: January 5th, 2009

Original Duration: 90 Calendar Days

Original Completion Date: April 4th, 2009

Time Extension Granted In Days: 45

Revised Completion Date: 5/20/09

Actual Completion Date: 5/12/09

Liquidated Damages: None

Recordable Accidents/ RAF: Zero / 0

Lost Time Accidents/ LAF: Zero / 0

OSHA Violations/ Fines: None

DOWNLOAD PDF

Project Brochure - Job 009r1-bernal-heights.jpg

LAH Pine Lane Sewer Diversion

Project Name: Guadalupe Creek Fish Ladder

Location: Campbell, CA

Owner: Santa Clara Valley Water District

Owner Contact: Tim Bramer – (408) 265-2607

Prime Contractor:  Con-Quest Contractors, Inc.

Architect/Engineer: Owner

Architect/Engineer Contact: N/A

Construction Manger Contact: N/A

Description Of Project Scope: All work performed within Guadalupe Creek. Design and implement a gravity water diversion around work capable of handling 100 cfs of water flow in creek, including a back up pump system. Installation of a cast in place concrete fish ladder structure, erosion control, slope protection, rip-rap plunge pool, 5 new weir structures and modify existing. HAZ-MAT excavation and controlled disposal of 460 tons of Mercury contaminated soils. Monitor and maintain sensitive wildlife area within works limits discovered during construction.

Original Bid Amount: $819,620.00

Change Orders: $18,624

Claims $0

Final Contract Value: $838,244

Original Start Date: October 29, 2009

Original Duration: 80 Calendar Days

Original Completion Date: August 11, 2008

Time Extension Granted In Days: 0

Actual Completion Date: October 29, 2009

Liquidated Damages: None

Recordable Accidents: Zero

Lost Time Accidents/ LAF: Zero / 0

OSHA Violations/ Fines: None

DOWNLOAD PDF

pine-lane-sewer-diversion.jpg

San Francisco VA Hospital

Project Name: San Francisco Veteran Affairs Hospital

Location: San Francisco, CA

Owner: SFVA – Army Corps of Engineers

Owner Contact:

Prime Contractor: Helix Electric

Prime Contractor Contact: Brady Hill – 415.933.6196

Architect/Engineer: Winzler & Kelly

Architect/Engineer Contact: N/A

Construction Manger Contact: N/A

Description Of Project Scope: Con-Quest performed as a subcontractor providing civil support for Helix Electric to install a new electrical ductbank in order to upgrade the SFVA hospitals system. Work on this congested work site included:

- 4,000 lf of 3’ x 5’ trenching including sawcutting and offhaul of native materials for power and communication ductbank

- 7,000 lf of 18” x 2’ trenching for new site lighting

- Drill and form 44 new light pole bases

- Form and pour 7 new large equipment pads including retaining walls and inlaid drain troughs.

- Excavate and install 24 vaults 12’ x 12’ x 10’ deep

- Restore 300 LF of Curb & Gutter and 2,600 SF of Sidewalk.

Original Bid Amount: $492,718.00

Change Orders: $307,000.00 – to date

Claims: $ ---0---

Final Contract Value: $ 799,718.00 – to date

Original Start Date: September 2011

Original Duration:

Original Completion Date: August 2014

Time Extension Granted In Days: TBD

Actual Completion Date: TBD – For C-QC work

Liquidated Damages: None

Recordable Accidents/ RAF: Zero / 0

Lost Time Accidents/ LAF: Zero / 0

OSHA Violations/ Fines: None

DOWNLOAD PDF

Project Brochure - Job 34 - VA Hospital.jpg

OSP Sludge

Project Name: Oceanside WWTP – Thickened Primary Activated Sludge Pump and Piping Improvements

Location: San Francisco, CA

Owner: SF PUC

Owner Contact: Gordon King – 415.559.2170

Prime Contractor Con-Quest Contractors, Inc.

Prime Contractor Contact: Alex Baranoff

Architect/Engineer: SFPUC

Architect/Engineer Contact: N/A

Construction Manger Contact: N/A

Description Of Project Scope:

Replacement of 2 existing primary pumps with 2 new Wemco Hidrostal Screw Centrifugal Pumps, installation of 3 new 6” Magnetic Flowmeters and glass lined ductile iron piping field cut and grooved.  Installed 3 pneumatic 6” plug valves and 6 manual 6”plug valves.  In addition, new instrumentation and wiring for control systems and painting of all new pumps, piping and accessories. 

Original Bid Amount: $357,500.00

Change Orders $ -11,354.57

Claims: $ ---0---

Final Contract Value: $346,145.57

Original Start Date: March 15, 2011

Original Duration: 180 Calendar Days

Original Completion Date: September 10, 2011

Time Extension Granted In Days: 30

Actual Completion Date: October 10, 2011

Liquidated Damages: None

Recordable Accidents/ RAF: Zero / 0

Lost Time Accidents/ LAF: Zero / 0

OSHA Violations/ Fines: None

DOWNLOAD PDF

Project Brochure - Job 30 - Ocean Side WWTP.jpg
prev / next
Back to Concrete + Flatwork
5 Fulton
2
5 Fulton Ductbank
bernal-heights.jpeg
1
Bernal Heights Street Improvements
LAH-pine-lane.jpeg
1
LAH Pine Lane Sewer Diversion
2
San Francisco VA Hospital
1
OSP Sludge
pipeline.jpg
structures.jpg
shoring-excavation.jpg
rail-trackwork.jpg
duct-bank.jpg
creeks-canals.jpg